Grand Avenue Reconstruction in Mt. Pleasant Continues

Written by on May 17, 2013 in News

Grand Avenue Update…..Starting Monday May 20th DeLong Construction will continue grading, installing sub-drain pipe, engineering fabric and modified sub-base between Baker St. & Winfield Ave. Mike Nelson Concrete will be pouring concrete on Grand Ave. between Ash St. & Mapleleaf Dr.
The next pour that will require temporarily blocking the Frontage Road on the East side of Grand Ave. This will be Wednesday May 22nd weather permitting. I will send out another email prior to concrete pour giving the traffic pattern and other details of the concrete pour. Baker St. could get slid to the North in the coming week to allow for Mike Nelson Concrete to start pouring the South half of the Baker St. & Grand Ave. intersection. The intersection will probably be closed Monday or Tuesday to allow DeLong Construction to slide temporary road on Baker St. to the North. Other than this short closure on Baker St. the Mapleleaf Dr., Baker St. & Winfield Ave. intersections will remain open in the coming week.
The Baker St. intersection will be entirely closed after the Memorial weekend to allow for placing concrete in the Baker St. & Grand Ave. intersection. This work could take up to two weeks to complete.

Comments are closed.