Grand Avenue open from Monroe to Baker

Written by on August 26, 2013 in News

Grand Avenue in Mt. Pleasant is now open from Monroe St. to Baker St. and should not need to be closed anymore for this project. Warner Engineering thanked everyone involved for all the team work.
City Administrator Brent Schleisman, Mayor Steve Brimhall, Councilman Stan Curtis, Public Works Director Rick Mullin and Police Chief Ron Archer met every Thursday morning for a progress meeting to discuss all concerns to keep the project on schedule with the Contractors, the Utilities and Warner Engineering. No work is currently taking place but September 3rd until approximately October 15th construction will take place as crews will be finishing the Winfield and Grand Avenue intersection and paving North to the North return of James Ave.