North Grand Avenue Update

Written by on September 27, 2013 in News

The end is near. DeLong Construction finished all shoulder work on Grand Avenue North of Winfield Ave. Thursday. Mike Nelson Concrete Paving will be sealing remaining concrete joints Friday Sept. 27th & Saturday Sept. 28th. Road Safe will be finishing the remaining striping and symbol installation on Grand Ave. Monday Sept. 30th & Tuesday Oct. 1st. The seeding crew will be mobilizing to finish the seeding & mulching Saturday Sept. 28th and plan to finish on Oct. 2nd weather permitting. DeLong Construction will then be sweeping and cleaning the street for opening. The plan is to have Grand Ave. open to all traffic on Friday Oct. 4th. Mike Nelson Concrete Paving will be finishing misc. patches on the Frontage Road, Cherry & Baker St. intersection and Orscheln Farm & Home driveways from Oct. 2nd through Oct. 11th weather permitting.