With the recent rain today and forecast for tonight and Thursday May 26th the Contractor has decided to wait until Tuesday May 31st to finish the paving on Oakbrook Place in Mount Pleasant. Tuesday the North side of Oakbrook Place will reach maturity and the ready mix trucks will be able to finish pouring the concrete off the North side of Oakbrook Place. They will also be able to access the cul de sac with ready mix trucks to pour the driveways to the homes. With warmer temperatures next week and no rain the Contractor should get a lot if not all of the driveways replaced on Oakbrook Place.