Mount Pleasant Street Project Update

Aldrin-Jones Contracting is placing the last section of Concrete today on the tie-in to Vine St. and finishing Intake boxouts. Once the concrete reaches maturity the next step will be finishing backfilling and grading. Then all disturbed areas will be seeded. Depending on scheduling this project could be complete by the end of May weather permitting.

Henry Street-Starting Tuesday May 23rd Kinney & Sons will be closing Henry St. from just West of Marion St. to the East. Crews will be starting the removal of the street surface, driveway approaches and sidewalks working their way East. After crews get at least a block removed they will be grading, placing engineering fabric and modified subbase. Once we get subbase placed driveways will be temporarily opened back up for local homeowners. Henry St. will be open to only local traffic until the pavement has been placed.